FILED ON: 4/29/2014
SENATE . . . . . . . . . . . . . . No. 2120
|
The Commonwealth of Massachusetts
_______________
In the Year Two Thousand Fourteen
_______________
An Act relative to fair retainage payments in private construction.
Be it enacted by the Senate and House of Representatives in General Court assembled, and by the authority of the same, as follows:
SECTION 1. Chapter 149 of the General Laws is hereby amended by inserting after section 29E the following section:
Section 29F: (a) As used in this section the following word(s) shall have the following meanings, unless the context clearly requires otherwise:
"Contract for construction", a contract for which a lien may be established under sections 2 or 4 of chapter 254 on a project for which the person whose contract with the project owner has an original contract price of $3,000,000 or more; provided, however, this shall not include projects containing or designed to contain at least 1 but not more than 4 dwelling units.
“Claim”, an allegation that the person seeking payment of retainage breached its contract for construction for the project. A claim shall be subject to the applicable dispute resolution procedure, notice and other requirements in the contract for construction.
“Deliverable(s)”, project close-out documents required to be submitted by the person seeking payment of retainage under that person’s contract for construction. A lien waiver or release which is a deliverable shall comply with chapter 254. A deliverable shall not include a document affirming, certifying or confirming completion or correction of labor, materials or other items furnished or incomplete or defective work.
“Incomplete or defective work”, labor, materials or any other items, except deliverables, required for full performance by the person seeking payment of retainage which remain to be furnished by such person under that person’s contract for construction or which have been furnished by such person but require correction, repair, further completion, revision or replacement. Incomplete or defective work shall not include labor, materials or other items to be repaired or replaced after substantial or final completion pursuant to a warranty or guarantee or other contractual obligations to correct defective work after substantial or final completion.
“Person”, any natural person, joint venture, partnership, corporation or other business or legal entity.
“Prime contractor”, a person who enters into a contract for construction with the project owner.
“Retainage”, a portion of a payment due pursuant to a contract for construction that is withheld to ensure full performance of such contract for construction.
“Substantial completion”, the stage in the progress of the project when the work required by the contract for construction with the project owner is sufficiently complete in accordance with the contract for construction so that the project owner can occupy or utilize such work for its intended use. Substantial completion may apply to the entire project, or a phase of the entire project if the contract for construction with the project owner expressly permits substantial completion to apply to defined phases.
(b) Every contract for construction which provides for retainage shall also provide that retainage shall not exceed 5% of each progress payment.
(c) No later than fourteen days after substantial completion the prime contractor shall submit to the project owner a notice of substantial completion, substantially in the form provided in this subsection, stating the date on which the project was substantially complete.
FORM FOR NOTICE OF SUBSTANTIAL COMPLETION
NOTICE OF SUBSTANTIAL COMPLETION
Under M.G.L. c. 149, § 29F
For [project name]
To [project owner]:
The undersigned hereby gives notice that the project was substantially complete, as defined under M.G.L. c. 149, § 29F, on [date of substantial completion]. This notice is certified as made in good faith on [date of notice].
By_____________________________
[prime contractor]
Accepted:
By_____________________________
[project owner]
Dated: _________________________
(d) The project owner shall accept or reject the notice of substantial completion within fourteen days of receipt of the notice. The project owner shall indicate its acceptance by signing the notice in the space provided and returning it to the prime contractor within such fourteen days. If the project owner rejects the notice of substantial completion it shall, within such fourteen days, notify the prime contractor in writing of the rejection, and include in the writing the factual and contractual basis for the rejection and a certification that the rejection is made in good faith. Any such rejection shall be subject to the dispute resolution provisions of the contract for construction, which, notwithstanding any provision in such contract to the contrary, shall be commenced by the prime contractor within seven days of receipt of the project owner’s rejection. The prime contractor and project owner shall prosecute the dispute resolution procedures diligently, expeditiously and in good faith. Any notice of substantial completion not rejected by the project owner within fourteen days of receipt of the notice and in accordance with this subsection (d) shall be deemed accepted by the project owner. Upon an express or deemed acceptance of a notice of substantial completion, the date of substantial completion shall be the date so stated in the prime contractor's notice for all purposes, and such acceptance shall be final and binding on the project owner and its successors and assignees.
(e) No later than fourteen days after the express or deemed acceptance of the notice of substantial completion, or in the case of a dispute, final and binding resolution of the dispute, the project owner shall submit to the prime contractor a written list describing all the incomplete or defective work items and deliverables required of the prime contractor under the prime contractor’s contract for construction. Such list shall be certified by the project owner as made in good faith. No later than twenty one days after the express or deemed acceptance of the notice of substantial completion, or in the case of a dispute, final and binding resolution of the dispute, the prime contractor shall submit to each person from whom the prime contractor is withholding retainage a written list describing all the incomplete or defective work items and deliverables required by such person under that person’s contract for construction, which list may include items beyond those on the project owner's list. Such list shall be certified by the prime contractor as made in good faith. Neither the project owner nor the prime contractor shall include any items or deliverables on the list which are subject to a warranty, guarantee or other contractual obligation to correct defective work after substantial or final completion.
(f) The project owner and prime contractor shall fulfill their obligations under sections (c), (d) and (e) in a good faith and timely manner. Except where the contract for construction provides for an earlier submission, following the expiration of sixty days after substantial completion, or, in the case of a dispute under subsection (d), final and binding resolution of the dispute, a person may submit a written application for payment of retainage in the form required by such person’s contract for construction. Any application for payment of retainage shall be accompanied by a written list identifying those incomplete or defective work items and deliverables on its received list that the person has completed, repaired and delivered. Such list shall be certified by the person submitting the application for payment of retainage as made in good faith. Subject to subsection (g) of this section, an application for payment of retainage shall be paid no later than thirty days following submission of the application; provided, however, that the time period for payment of an application for retainage by the person at each tier of contract below the owner of the project may be extended by seven days more than the time period applicable to the person at the tier of contract above such person.
(g) The following may be withheld from the payment of retainage: (i) an amount of not more than the reasonable value of deliverables, provided that the total value of all deliverables shall not be assessed at more than 50% of the original retainage withheld under that person’s contract for construction; (ii) an amount of not more than 150% of the reasonable cost to complete or correct incomplete or defective work items; and (iii) an amount of not more than the reasonable value of claims, and any costs, expenses and attorneys’ fees incurred as a result of the claims if permitted in the contract for construction of the person seeking payment of retainage. Provided, however, that no amount shall be withheld from the payment of retainage unless the person seeking payment has received, before the date payment is due, a writing which describes the incomplete or defective work items and deliverables, the factual and contractual basis for the claims and the value attributable to each incomplete or defective work item, deliverable and claim, and which is certified as made in good faith. A person may submit additional applications for payment of retainage in the form required by such person’s contract for construction following completion or correction of incomplete or defective work items, the furnishing of deliverables or the resolution of claims. Such additional applications shall be paid, and amounts may be withheld from payment, in accordance with subsections (f) and (g).
(h) Retainage held by the project owner on account of the prime contractor’s self-performed labor, materials and equipment shall be eligible for payment to the same extent as if such labor materials and equipment had been provided by a person under a contract for construction with the prime contractor.
(i) Provided the prime contractor is not in breach of its contract for construction with the project owner, and subject to the provisions of this Section 29F, the project owner shall not withhold any part of the retainage of a person under a contract for construction with the prime contractor, or the prime contractor’s proportional retainage calculated thereon, for a claim that the project owner asserts against the prime contractor that does not arise out of performance of such person or the prime contractor or breach of such person’s or the prime contractor’s contract for construction.
(j) A contract for construction may establish date of the month for submission of an application for payment of retainage provided such contract may not restrict such submission to less frequently than one application per calendar month. An application submitted prior to the date established in the contract for construction shall be deemed submitted as of the date established in such contract. Any rejection of any application for payment of retainage and any dispute regarding incomplete or defective work items, deliverables or claims shall be subject to the applicable dispute resolution procedure. A provision in a contract for construction which requires a person to delay commencement of such procedure until a date later than 30 days after the rejection of an application for payment of retainage or written notice of the dispute is provided, whichever first occurs, is void and unenforceable. Payment of retainage shall be subject to subsection (e) of c. 149 sec 29E.
(k) A communication required in this section to be in writing may be submitted in electronic form and by electronic means.
(l) A provision in a contract for construction which purports to waive, limit or subvert any provisions of this section, or to redefine or expand the conditions for achievement of substantial completion or for payment of retainage shall be void and unenforceable.