SECTION 1. (a) For the purposes of this section the following terms, shall, unless the context clearly indicates otherwise, have the following meanings:-
“Affiliate”, any corporation, society, trust, association, partnership or individual that is, directly or indirectly, partially or wholly owned or controlled by the same parent company as a distribution company.
“Clean energy generation resources”, either (1) firm service hydroelectric generation from hydroelectric generation alone; or (2) new Class I RPS eligible resources that are firmed up with firm service hydroelectric generation.
“Contract date”, the date of execution of a long-term contract pursuant to this section.
“Firm service hydroelectric generation”, hydroelectric generation provided without interruption for a period designated in a contract, subject to reasonable force majeure interruptions that may be negotiated under said contract, including but not limited to multiple hydroelectric run-of-the-river generation units managed in a portfolio that creates firm service through the diversity of multiple units.
“New Class I RPS eligible resources”, Class I renewable energy generating sources as defined in section 11F of chapter 25A that have not commenced commercial operation prior to a contract date or represent the net increase from incremental new generating capacity at an existing facility after a contract date.
“Long-term contracts”, contracts for a period of 15 to 25 years.
“Project affiliation”, when a transmission or generation project is, directly or indirectly, partially or wholly owned or controlled by a distribution company or by an affiliate of a distribution company or the parent company of a distribution company.
(b) Notwithstanding any general or special law to the contrary, all distribution companies, as defined in section 1 of chapter 164 of the General Laws, shall, together with the department of energy resources, jointly and competitively solicit proposals for clean energy generation resources to deliver no more than an annual amount of electricity of approximately 18,900,000 megawatt-hours via long-term contracts to be executed by the distribution companies and, provided the department of energy resources determines reasonable proposals have been received pursuant to subsection (c), enter into cost-effective long-term contracts for an annual amount of electricity of approximately 9,450,000 megawatt-hours per project. Initial solicitations under this section shall commence no later than April 1, 2016.
(c) The department of energy resources shall coordinate, through a schedule or staggered schedule designated by the department of energy resources, one or more solicitations pursuant to subsection (b). Such solicitations may be done jointly with other New England states or entities designated by said states. If the department of energy resources determines that reasonable proposals were not received pursuant to a solicitation, the department of energy resources may terminate the solicitation. The department of energy resources shall determine whether an additional solicitation is necessary to ensure that clean energy generation resources are procured in a cost-effective manner on a long-term basis to meet the Commonwealth’s goals pursuant to Chapter 298 of the Acts of 2008.
(d) The solicitations and subsequent procurements of resources may include proposals for electric transmission to interconnect load centers in the New England control area with regions or areas where clean energy generation resources may be available. Such transmission proposals may provide for procurement separate from the power purchase agreement for the clean energy generation resources or may bundle the transmission into the power purchase agreement. To the extent transmission is unbundled from the power purchase agreement it shall be pursued through the rules of the federal energy regulatory commission. In such case, the department of energy resources shall have the authority to determine whether the transmission shall be pursued through (1) an elective transmission upgrade, (2) under the rules applicable to transmission advanced to meet public policy requirements, as such terms are used by the federal energy regulatory commission; or (3) such other means available under federal rules as appropriate.
(e) A draft of the request for proposals to be used in any solicitation under this section shall be filed with the department of public utilities for review and approval prior to issuance and the department of public utilities shall issue a decision within thirty days of the close of the public comment period.
(f) If a solicitation is not terminated pursuant to section (c), then the distribution companies and the department of energy resources shall jointly evaluate any bids received for the purposes of selecting a winning bidder. If there is a disagreement between or among the distribution companies or with the department of energy resources, as to the selection of a winning bidder, then the disagreement shall be submitted to the office of the attorney general for a decision within 90 days. The attorney general shall authorize the selection of a winning bidder only upon a finding that the project is cost-effective and the selection of a winning bidder is not unduly influenced by a project affiliation.
(g) Any long-term contracts executed in accordance with this section shall be subject to the approval of the department of public utilities, provided that the department of public utilities shall approve a contract only upon a finding that it is a cost-effective means for procuring clean energy generation resources on a long-term basis to meet the Commonwealth’s goals set forth in Chapter 298 of the Acts of 2008.
(h) A distribution company may elect to use any energy, capacity, or renewable energy certificates purchased under any long-term contract executed in accordance with this section for resale to its customers. If the energy, capacity, or renewable energy certificates are not so used, such companies shall sell such purchased energy, capacity, or renewable energy certificates in the wholesale market through a competitive bid process.
(i) If a distribution company sells such purchased energy, capacity, or renewable energy certificates in the wholesale market, the distribution company shall net the cost of payments made under the long-term contracts against the proceeds obtained from the sales, and the difference shall be credited or charged to all distribution customers through a non-bypassable rate included in distribution rates, subject to the review and approval of the department of public utilities.
(j) The department of energy resources may promulgate rules and regulations consistent with this section and may hire experts or consultants to assist in: (1) the development of said rules and regulations and (2) the management and coordination of the solicitation or solicitations, the project evaluation process, and approval proceedings. The costs associated with hiring said experts or consultants shall be paid from the alternative compliance payment fund overseen by the department of energy resources.
(k) Any contracts procured under this section shall contain provisions that require an appropriate unit-specific tracking system to enable an accounting of the delivery of clean energy generation resources.
(l) The invalidity or unenforceability of any provisions of this section shall not affect the validity or enforceability of any other provision of this section, which shall remain in full force and effect.
The information contained in this website is for general information purposes only. The General Court provides this information as a public service and while we endeavor to keep the data accurate and current to the best of our ability, we make no representations or warranties of any kind, express or implied, about the completeness, accuracy, reliability, suitability or availability with respect to the website or the information contained on the website for any purpose. Any reliance you place on such information is therefore strictly at your own risk.