HOUSE DOCKET, NO. 3936        FILED ON: 2/19/2021

HOUSE  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  No. 3266

 

The Commonwealth of Massachusetts

_________________

PRESENTED BY:

Antonio F. D. Cabral

_________________

To the Honorable Senate and House of Representatives of the Commonwealth of Massachusetts in General
Court assembled:

The undersigned legislators and/or citizens respectfully petition for the adoption of the accompanying bill:

An Act relative to offshore wind.

_______________

PETITION OF:

 

Name:

District/Address:

Date Added:

Antonio F. D. Cabral

13th Bristol

2/19/2021

Christopher Hendricks

11th Bristol

2/25/2021

Elizabeth A. Malia

11th Suffolk

3/18/2021


HOUSE DOCKET, NO. 3936        FILED ON: 2/19/2021

HOUSE  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  No. 3266

By Mr. Cabral of New Bedford, a petition (accompanied by bill, House, No. 3266) of Antonio F. D. Cabral, Christopher Hendricks and Elizabeth A. Malia relative to the offshore wind proposal bidding process.  Telecommunications, Utilities and Energy.

 

The Commonwealth of Massachusetts

 

_______________

In the One Hundred and Ninety-Second General Court
(2021-2022)

_______________

 

An Act relative to offshore wind.

 

Be it enacted by the Senate and House of Representatives in General Court assembled, and by the authority of the same, as follows:
 

SECTION 1. Subsection (b) of section 83C of chapter 169 of the acts of 2008, as amended by chapter 188 of the acts of 2016, is hereby amended by striking out the figure “1,600” and inserting in place thereof the following figure:- 4,800.

SECTION 2. Said Subsection (b) of said section 83C of said chapter 169, as so appearing, is hereby further amended by striking out the words:- "June 30, 2027" and inserting in place thereof the following words:- "June 30, 2025; provided, however, that said distribution companies enter into cost effective long-term contracts for offshore wind energy generation equal to approximately 1,600 megawatts of aggregate nameplate capacity not later than June 30, 2022".

SECTION 3. Said Subsection (b) of said section 83C of said chapter 169, as so appearing, is hereby further amended by striking out the words:- ", if applicable,".

SECTION 4. Subsection (b) of said section 83C of said chapter 169, as so appearing, is hereby further amended by striking out the words "24 months" and inserting in place thereof the following words:- "18 months."

SECTION 5. Section 83C of said chapter 169 of the acts of 2008, as so appearing, is hereby amended by inserting the following subsection:-

(e) The winning bid shall create and foster employment and economic development in the Commonwealth and represent not less than fifteen percent of the proposal’s overall score in the bids selection process. The winning bid shall be chosen by the selection committee which shall consider all proposals and criteria in subsection (d) when making a final decision.  The committee shall consist of the following members: the secretary of energy and environmental affairs, which shall be the chair; the attorney general; the secretary of the executive office of housing and economic development; and the house and senate chairs of the joint committee on telecommunications, utilities and energy.