HOUSE DOCKET, NO. 2323        FILED ON: 2/17/2021

HOUSE  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  No. 3296

 

The Commonwealth of Massachusetts

_________________

PRESENTED BY:

Carolyn C. Dykema

_________________

To the Honorable Senate and House of Representatives of the Commonwealth of Massachusetts in General
Court assembled:

The undersigned legislators and/or citizens respectfully petition for the adoption of the accompanying bill:

An Act improving gas safety in excavation.

_______________

PETITION OF:

 

Name:

District/Address:

Date Added:

Carolyn C. Dykema

8th Middlesex

2/17/2021

Sally P. Kerans

13th Essex

2/17/2021

Colleen M. Garry

36th Middlesex

2/17/2021

David Henry Argosky LeBoeuf

17th Worcester

2/23/2021

Christina A. Minicucci

14th Essex

2/24/2021

Elizabeth A. Malia

11th Suffolk

2/24/2021

Walter F. Timilty

Norfolk, Bristol and Plymouth

3/30/2021

Lindsay N. Sabadosa

1st Hampshire

4/1/2021

Maria Duaime Robinson

6th Middlesex

4/1/2021

James B. Eldridge

Middlesex and Worcester

4/25/2021

Natalie M. Higgins

4th Worcester

9/3/2021

Erika Uyterhoeven

27th Middlesex

1/31/2022

Nika C. Elugardo

15th Suffolk

4/29/2022


HOUSE DOCKET, NO. 2323        FILED ON: 2/17/2021

HOUSE  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  No. 3296

By Ms. Dykema of Holliston, a petition (accompanied by bill, House, No. 3296) of Carolyn C. Dykema and others relative to improving gas safety in excavation.  Telecommunications, Utilities and Energy.

 

The Commonwealth of Massachusetts

 

_______________

In the One Hundred and Ninety-Second General Court
(2021-2022)

_______________

 

An Act improving gas safety in excavation.

 

Be it enacted by the Senate and House of Representatives in General Court assembled, and by the authority of the same, as follows:
 

Section 144 of Chapter 164 of the General Laws, as appearing in the 2018 Official Edition, is hereby amended by striking out subsection (c) and inserting in place thereof the following subsection:-

(c)(1) Upon the undertaking of a significant project on a public way exposing confirmed natural gas infrastructure, and with sufficient notice, a municipality or the commonwealth shall submit written notification of the project to a gas company. The gas company shall survey the project area for the presence of Grade 1 or Grade 2 leaks and set repair and replacement schedules for all known or newly detected Grade 1 or Grade 2 leaks. The gas company shall ensure that any shut off valve in the significant project area has a gate box installed upon it or a reasonable alternative that would otherwise ensure continued public safety and that any critical valve that has not been inspected and tested within the past 12 months is verified to be operational and accessible. The gas company shall provide the repair and replacement schedule of gas leaks to the municipality or the commonwealth.

(2) Upon the undertaking of any planned project involving excavation for purposes of performing maintenance on or construction involving any gas mains or services by gas company employees, or any blasting work, the gas company shall ensure that its employees first locate and identify and mark all gas gates and valves, and verify that all are cleared, operational and accessible in clear sight at ground level in advance of any excavation; and that said gas gates and valves are left cleared, and operational following any such project.

(3) The gas company shall ensure that any shut off valve in the significant project area has a gate box installed upon it by its employees to ensure continued public safety.

(4) The gas company shall provide the municipality or the commonwealth with written confirmation that the gas gates and valves have been cleared, inspected and tested by its employees and found to be capable of accepting a gate key; and, shall provide the municipality or commonwealth with undated, correct information if the location of gates or valves is determined to have been previously improperly located.

(5) Failure to undertake verification that gas gates and valves have been cleared, and are both operational and accessible prior to the start of and following an excavation, or blasting work, shall be subject to a fine of up to $10,000. Failure to submit written confirmation of such verification shall be subject to a fine of $200 per day.