SENATE DOCKET, NO. 586 FILED ON: 2/3/2021
SENATE . . . . . . . . . . . . . . No. 2181
|
The Commonwealth of Massachusetts
_________________
PRESENTED BY:
Cindy F. Friedman
_________________
To the Honorable Senate and House of Representatives of the Commonwealth of Massachusetts in General
Court assembled:
The undersigned legislators and/or citizens respectfully petition for the adoption of the accompanying bill:
An Act relative to the failure to remove existing utility poles.
_______________
PETITION OF:
Name: | District/Address: |
Cindy F. Friedman | Fourth Middlesex |
SENATE DOCKET, NO. 586 FILED ON: 2/3/2021
SENATE . . . . . . . . . . . . . . No. 2181
By Ms. Friedman, a petition (accompanied by bill, Senate, No. 2181) of Cindy F. Friedman for legislation relative to the failure to remove existing utility poles. Telecommunications, Utilities and Energy. |
[SIMILAR MATTER FILED IN PREVIOUS SESSION
SEE SENATE, NO. 1968 OF 2019-2020.]
The Commonwealth of Massachusetts
_______________
In the One Hundred and Ninety-Second General Court
(2021-2022)
_______________
An Act relative to the failure to remove existing utility poles.
Be it enacted by the Senate and House of Representatives in General Court assembled, and by the authority of the same, as follows:
Chapter 164 of the General Laws is hereby amended by inserting after section 34B the following section:-
Section 34C. A distribution company or a telephone company engaging in the removal of an existing pole and the installation of a new pole in place thereof that does not complete the transfer of wires, all repairs and the removal of the existing pole from the site within 90 days from the date of installation of the new pole shall pay a fine of $200 to the municipality where the existing pole is located for every day after 90 days from the date of installation of the new pole; provided, however, that for any approved commercial or industrial construction project, the completion of which is expected to take longer than one year, said company shall pay a fine of $200 to the municipality where the existing pole is located for every day after 6 months from the date of installation of the new pole that the transfer of wires, all repairs and the removal of the existing pole from the site are not completed.