HOUSE DOCKET, NO. 2362        FILED ON: 1/16/2025

HOUSE  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  No.         

 

The Commonwealth of Massachusetts

_________________

PRESENTED BY:

Kristin E. Kassner

_________________

To the Honorable Senate and House of Representatives of the Commonwealth of Massachusetts in General
Court assembled:

The undersigned legislators and/or citizens respectfully petition for the adoption of the accompanying bill:

An Act facilitating site plan review.

_______________

PETITION OF:

 

Name:

District/Address:

Date Added:

Kristin E. Kassner

2nd Essex

1/16/2025


HOUSE DOCKET, NO. 2362        FILED ON: 1/16/2025

HOUSE  .  .  .  .  .  .  .  .  .  .  .  .  .  .  .  No.         

[Pin Slip]

 

The Commonwealth of Massachusetts

 

_______________

In the One Hundred and Ninety-Fourth General Court
(2025-2026)

_______________

 

An Act facilitating site plan review.

 

Be it enacted by the Senate and House of Representatives in General Court assembled, and by the authority of the same, as follows:
 

SECTION 1. Section 1A of chapter 40A of the General Laws, as appearing in the 2024 Official Edition, is hereby amended by inserting after the definition of “As of right” the following definition:-

“Bulk and height of structures” shall mean the articulation and roof lines of structures; provided, however, that performance standards governing bulk and height of structures may not be more restrictive than the dimensional requirements set forth in the ordinance or bylaw, nor require specific building materials. Articulation, as used herein, refers to the following strategies to address building massing: wall offsets, height variation, wall setbacks, accent lines, stepbacks, or such other industry standard types of articulation as may be proposed by the petitioner.

SECTION 2. Section 1A of chapter 40A of the General Laws, as appearing in the 2024 Official Edition, is hereby amended by inserting after the definition of “Permit granting authority” the following definition:-

"Site plan review" shall mean the review and approval process under a municipality’s zoning ordinance or by-law that establishes criteria for the layout, safety, and impacts of a proposed use or development, and whether a proposed use of land or structures is in compliance with reasonable performance standards as defined in section 7A, provided, however, that site plan review, and the performance standards applicable thereto, in connection with any use specifically governed by section 3 or any other section of this chapter shall be limited to the extent required by the provisions of such section.

SECTION 3. Chapter 40A of the General Laws, as appearing in the 2024 Official Edition, is hereby amended by adding the following section:–

Section 7A. (a) Definitions. As used in this section, the following words shall have the following meanings:

“Designated authority” shall mean the local municipal board, committee, and/or official(s) designated in the zoning ordinance or bylaw to conduct site plan review.

“Performance standards” shall mean reasonable municipal zoning regulations, and published industry standards and best practices, applicable to site plans and relative to traffic circulation and safety, pedestrian safety and access, off-street parking and loading, emergency vehicle access, stormwater drainage, screening, bulk and height of structures, exterior lighting, and storage or other outdoor service areas.

(b) Substantive provisions of site plan review, including content of submittal requirements and applicable performance standards, governing site plan review and approval by the designated authority or authorities must be as set forth within a local ordinance or by-law adopted pursuant to section 5. Performance standards must be reasonably definite and objective so that any petitioner has knowledge of such standards prior to application submittal. No zoning bylaw or ordinance may include performance standards governing the aesthetics of structures.  The designated authority may, where such action is in the public interest and not inconsistent with the intent and purpose of this section, waive strict compliance with the performance standards for site plan review. The designated authority may adopt, and from time to time amend, procedural rules and regulations to implement the local site plan review ordinance or by-law, including provisions for the imposition of reasonable fees for the employment of outside consultants in the same manner as set forth in section 53G of chapter 44.

(c) A zoning ordinance or bylaw may establish applicability standards for projects that are subject to site plan review, which may include a category of projects that are subject to a minor or administrative site plan review process.  The zoning ordinance or bylaw may require a public hearing in accordance with section eleven for projects that meet or exceed specified thresholds under the zoning ordinance or by-law. The decision of the designated authority for a use allowed by right, or for a use requiring a special permit but reviewed by a separate designated authority, shall require a simple majority vote of the designated authority and shall be made within the time limits prescribed by ordinance or by-law, not to exceed 90 days from the date of filing of a complete application or such extended time as may be agreed in writing by the petitioner.  The submission and review process for a site plan required in connection with the issuance of a special permit, and subject to review by the same permit granting authority as the special permit application, shall be conducted with the review of the special permit application in a coordinated process and may require the same quantum of vote required for approval of a special permit. The ordinance or by-law may establish the designated authority to be the building commissioner, director of planning, or other municipal official who coordinates administrative site plan review with other municipal employees, in which instance there shall be no vote requirement for site plan review. Any appeal from administrative site plan review shall be in accordance with section 17 unless an ordinance or by-law first provides for an appeal to another public body of the municipality. In no instance shall the issuance or denial of a building permit be a prerequisite to the filing of a civil action under this section.

(d) Site plan review may impose only those conditions that are necessary to ensure substantial compliance of the proposed use of land or structures with the requirements of the zoning ordinance or by-law, provided that no condition may impose restrictions greater than those expressly regulated within the zoning ordinance or bylaw and no conditions may be imposed regarding matters over which jurisdiction exclusively lies in another body pursuant to any general or special law, and further provided that any off-site conditions shall only address direct adverse impacts related to performance standards expressly governed by the zoning ordinance or bylaw and which conditions are proportionate in both nature and extent to the impacts of the project on adjacent properties or adjacent roadways.

(e) A site plan application may be denied only on the grounds that: (i) the proposed site plan does not meet the specific requirements set forth in the zoning ordinance or by-law; or (ii) the petitioner failed to submit the information and fees required by the zoning ordinance or by-law necessary for an adequate and timely review of the design of the proposed land or structures.

(f) The designated authority shall cause to be made a detailed record of its proceedings, indicating the vote of each member upon each question, or if absent or failing to vote, indicating such fact, and setting forth clearly the reason for its decision and of its official actions, copies of all of which shall be filed within fourteen days in the office of the city or town clerk and shall be deemed a public record, and notice of the decision shall be mailed forthwith to the petitioner and, if such site plan review required a public hearing pursuant to the zoning ordinance or bylaw, to the parties in interest designated in section eleven. Each such notice shall specify that appeals, if any, shall be made pursuant to section seventeen and shall be filed within twenty days after the date of filing of such notice in the office of the city or town clerk.  Failure by the designated authority to take final action within said ninety days or extended time, if applicable, shall be deemed to be an approval of the site plan. The petitioner who seeks such approval by reason of the failure of the designated authority to act within such time prescribed, shall notify the city or town clerk, in writing within fourteen days from the expiration of said ninety days or extended time, if applicable, of such approval. If site plan review required a public hearing, the petitioner shall send such notice to parties in interest designated in section eleven by mail and each such notice shall specify that appeals, if any, shall be made pursuant to section seventeen and shall be filed within twenty days after the date the city or town clerk received such written notice from the petitioner that the designated authority failed to act within the time prescribed. After the expiration of twenty days without notice of appeal pursuant to section seventeen, or, if appeal has been taken, after receipt of certified records of the court in which such appeal is adjudicated, indicating that such approval has become final, the city or town clerk shall issue a certificate stating the date of approval, the fact that the designated authority failed to take final action and that the approval resulting from such failure has become final, and such certificate shall be forwarded to the petitioner.

(g) A site plan approval granted under this section shall lapse within a specified period of time, not less than three years from the date of the filing of such approval with the city or town clerk, if substantial use or construction has not yet begun, except as extended for good cause by the designated authority. Such specified period shall not include time required to pursue or await the determination of an appeal under section 17 or to pursue or await the appeal of any other permit, license, determination or approval which are prerequisites to issuance of a building permit. The aforesaid minimum period of three years may, by ordinance or by-law, be increased to a longer period.

SECTION 4. Sections 1 through 3 shall take effect for all municipalities upon the effective date of this act; provided, however, that in municipalities that adopted a zoning ordinance or by-law requiring some form of site plan review prior to the effective date of this act, the provisions of this section shall not be effective with respect to such zoning ordinance or by-law until the date that is one year after the effective date of this act.