Mrs. Dooner and Mr. Montigny move that the proposed new text be amended by adding the following subsection to section 86:-

(e) Not later than December 31, 2027, the energy efficiency management review and financial oversight board shall submit a corrective action plan identifying specific administrative, contracting, programmatic and operational reforms necessary to reduce the costs of building decarbonization, energy efficiency, load management and demand reduction programs funded by ratepayers.

The corrective action plan shall include: (1) an itemized list of recommended cost reductions; (2) proposed reductions in administrative expenses, vendor and contractor payments and performance incentives; (3) recommendations to consolidate or eliminate duplicative, inefficient or underperforming programs; (4) an estimate of the savings expected from each recommendation; and (5) a schedule for reducing charges assessed to ratepayers by an amount reflecting the savings achieved.

Not later than 120 days after receiving the corrective action plan, the department of public utilities shall approve, approve with modifications or reject each recommendation and shall issue a written explanation of its determination. The department shall require the program administrators to implement each approved recommendation. Savings realized pursuant to this subsection shall be returned to ratepayers through a reduction in the applicable charges and shall not be reallocated to another program without specific authorization by the general court.