Amendment ID: S3143-55

Amendment 55

Addressing delays interconnecting residential solar

Ms. Comerford, Ms. Edwards and Messrs. Tarr and Eldridge move that the proposed new text be amended by adding the following section:-

SECTION X. As used in this section:

“Interconnection phase 1” means the elapsed time period between when the distribution company receives an interconnection application for distributed generation using the Simplified or Expedited‑without‑Supplemental‑Review track, or their successor tracks, and issues a signed interconnection service agreement or rejects the application.

“Interconnection phase 2” means the elapsed time period between when the distribution company receives confirmation of the construction or local wiring official’s successful inspections and permit closing for distributed generation using the Simplified or Expedited‑without‑Supplemental‑Review track, or their successor tracks, and when Authorization to Interconnect is granted.

“Timeline enforcement mechanism” means a tool, approved by the department, to measure and enforce each distribution company’s performance in meeting interconnection timelines established in each distribution company’s respective Standards for Interconnection of Distributed Generation tariff.

(b) Within 180 days of the date of enactment, each distribution company shall file with the department for approval:

(i) target average and maximum timelines for interconnection phase 1 that meet or exceed the timelines for the distribution company that processed interconnection requests fastest in 2024, based on the approved Time Frame Enforcement Metric reports;

(ii) target average and maximum timelines for interconnection phase 2 of no more than 10 business days for projects using the Simplified track and 18 business days for projects using the Expedited‑without‑Supplemental‑Review track; and

(iii) a plan to incorporate the target average and maximum timelines for interconnection phases 1 and 2 into the distribution company’s existing timeline enforcement mechanism process already approved by the department, including, but not limited to performance calculation methodologies, penalty and offset programs, and reporting schedules already approved by the department.

(c) Within 60 days of department approval, each distribution company shall publish the approved target average and maximum timelines and plans on its website so the information is accessible to customers.

(d) Within 60 days of the date of enactment, each distribution company shall post to its website:

(i) updates to interconnection processes;

(ii) updates to the documentation, forms, fees, or other materials necessary to submit a substantially complete interconnection application; and

(iii) notifications of any changes to technical standards or requirements for interconnection.

Members of the public shall be able to subscribe to electronic mail notifications of such changes and updates. Distribution companies shall post changes and updates not less than 14 days before implementing the change or update.

(e) Each distribution company shall update the Interconnection Workshops hosted through the Distributed Generation Working Group to include:

(i) discussion of noticed issues under subsection (b), inclusive of any process changes or changes in technical standards;

(ii) discussion of recent trends on application rejections and holds, including reasons for application holds or failures; and

(iii) opportunities for the public to ask questions on existing interconnection processes and on the Annual Interconnection Timeline Enforcement Mechanism Report.

(f) At the time an interconnection application is rejected, deemed incomplete, or put on hold, a distribution company shall disclose to the applicant:

(i) the reason the application is rejected, deemed incomplete, or being held; and

(ii) a reference to a publicly available document detailing the rules applied by the utility.

(g) Within 270 days of the date of enactment, each distribution company shall issue a report on low‑cost options to automate the processing of a significant portion of interconnection applications for distributed generation using the Simplified track, or its successor track, that meet the screening criteria, including best practices from other utilities in the United States and abroad.

(h) In each Annual Interconnection Timeline Enforcement Mechanism Report filed with the department after the date of enactment, each distribution company shall include:

(i) a machine‑readable list of all interconnection applications with the relevant information to assess compliance with the timeline enforcement mechanisms;

(ii) a list of any changes made to interconnection application processes, a description of the reasoning behind each change, and the date the public was notified;

(iii) explanations for any interconnection timelines that did not meet the company’s timeline enforcement metrics approved by the department;

(iv) a strategy for meeting any missed timelines in the future, where relevant;

(v) a survey of available technologies and best practices in interconnection; and

(vi) a formal recommendation as to whether interconnection timelines can be reduced for the following reporting year.

(i) Each Annual Interconnection Timeline Enforcement Mechanism Report filed with the department shall also be sent directly to the Distributed Generation Ombudsperson at the department and to the Interconnection Implementation Review Group.