Skip to Content
December 25, 2024 Clouds | 25°F
The 193rd General Court of the Commonwealth of Massachusetts

Section 39P: Contracts for construction and materials; awarding authority's decisions on interpretation of specifications, etc.; time limit; notice

Section 39P. Every contract subject to section thirty-nine M of this chapter or section forty-four A of chapter one hundred forty-nine which requires the awarding authority, any official, its architect or engineer to make a decision on interpretation of the specifications, approval of equipment, material or any other approval, or progress of the work, shall require that the decision be made promptly and, in any event, no later than thirty days after the written submission for decision; but if such decision requires extended investigation and study, the awarding authority, the official, architect or engineer shall, within thirty days after the receipt of the submission, give the party making the submission written notice of the reasons why the decision cannot be made within the thirty day period and the date by which the decision will be made.