Skip to Content
November 23, 2024 Mist | 44°F
The 193rd General Court of the Commonwealth of Massachusetts

Section 62D: Permit applications; time for agency determination

Section 62D. Agencies shall act on permit applications within ninety days following issue of notice of availability of the final environmental impact report, within ninety days following issue of notice of the determination that a report is not required, or ninety days following the permit application, whichever is latest, unless otherwise provided by law.